Example 1 (simple): 40% done after 12 working days
- Pace = 40% ÷ 12 = 3.33% of the work per day
- Projected total = 12 ÷ 0.40 = 30 working days
- Remaining = 30 − 12 = 18 working days
These are the calculator's default inputs.
Enter how much work is done and how long it took to see estimated time to complete, time remaining, the projected total and the pace a deadline needs.
Estimated time to complete is elapsed time divided by the fraction done. Remaining is that total minus elapsed. If 40% took 2 hours, the job takes 5 hours and 3 remain. Same pace is assumed; add a deadline to see the pace you would need instead.
Say how far you are: a percentage, or units completed out of a total (pages, tickets, records, kilometres). Enter how long that took and choose the time unit. Optionally enter the time left until the deadline to compare your pace with the pace you need.
The estimate is a straight-line projection. Work that speeds up or slows down, such as a first-draft phase followed by editing, needs a different method; for task-by-task ranges use the PERT calculator, and for earned-value based forecasts the schedule variance and SPI calculator.
share done = percent ÷ 100, or units done ÷ total units
estimated time to complete (total) = time elapsed ÷ share done
remaining = total − time elapsed pace = share done ÷ time elapsed
pace needed = (1 − share done) ÷ time left speed-up = pace needed ÷ pace
Everything is a ratio, so the unit cancels: the result is in whatever unit you used for the elapsed time. Use one unit for elapsed time and time left.
Each example uses numbers you can load into the calculator above; the results match the tool exactly.
These are the calculator's default inputs.
A team has reviewed 25 of 80 contracts in 10 working days and has 15 working days until the deadline.
The projection assumes the next unit of work takes as long as the average unit so far. That fails when the early work is the easy part, when a long tail of fixes follows the main build, or when the team size changes mid-way. Treat the result as a baseline, then adjust: if you expect the pace to fall by a quarter, lengthen the remaining time by a third.
For a bottom-up plan from tasks and hours use the task time estimator. To plan the whole project end to end use the project time calculator.
Divide the time elapsed by the share of work done, then subtract the time elapsed. If 40% of the work took 12 days, the total is 30 days and 18 days remain.
Use the same method: work out the pace from progress so far, project the total, and subtract the time already spent. Add a deadline to compare the result with the time you have.
Divide the work left by the time left. With 62.5% of the work left and 15 days to go you need 4.17% of the work per day. The tool also shows how many times faster that is than your current pace.
Yes. Choose "Units completed" and enter the units done and the total, for example 25 of 80 pages.
Each update gives the calculator a better measure of your real pace. Early estimates are rougher than estimates made after most of the work is done.
Hours, working days, calendar days or weeks. Pick the one you measured elapsed time in, and use it for the time left as well.
Written by Umesh Manral. Formulas checked against the site's test suite on 11 November 2026. Last updated 10 November 2026. Formulas and tests: methodology. Report a calculation error.