Example 1: EV 80,000, PV 100,000, 20-week plan
SPI = 0.80. Forecast = 20 ÷ 0.80 = 25 weeks. Delay = 5 weeks. These are the mini-calculator defaults.
Turn earned value and planned value into a duration forecast, then read it against last week and against remaining-time pace.
To forecast completion with SPI, divide the planned duration by SPI. SPI = EV ÷ PV. If EV is 80 and PV is 100, SPI is 0.80 and a 20-week plan forecasts 25 weeks. The forecast assumes the current rate continues. Read the index in words on the SPI meaning page.
SPI = EV ÷ PV. Forecast duration = planned ÷ SPI.
SPI tells you how much of the planned work is done relative to the plan, not how people feel. Once you have SPI, the duration forecast is a division. That is the same math as the schedule variance and SPI calculator.
Plain-language bands for 0.5 through 1.5 are on what SPI means. Weekly use of the number is in overseeing timeline execution. The term is in the SPI glossary.
SPI = EV ÷ PV
forecast duration = planned duration ÷ SPI
delay = forecast − planned duration
EV and PV must use the same unit (money or hours). Planned duration can be days or weeks; the forecast uses that unit.
Each example uses numbers you can load into the calculator above; the results match the tool exactly.
SPI = 0.80. Forecast = 20 ÷ 0.80 = 25 weeks. Delay = 5 weeks. These are the mini-calculator defaults.
Forecast = 40 ÷ 1.10 ≈ 36.4 days. You are ahead only if EV is real finished work, not hours spent. Check remaining time with the estimated time remaining calculator as a second view.
Early EV is often the easy work. An SPI of 1.1 in week two can still hide a brutal integration. Pair SPI with a look at which tasks are done. If only low-risk tasks are complete, do not cut the date.
Percent complete remaining time uses your current pace from the start of the job. SPI uses the baseline’s planned value. If the baseline was fantasy, SPI’s forecast is fantasy too. Fix the baseline, or switch to remaining-time pace.
Suppose the plan is 40 working days, EV is 110 and PV is 100, so SPI is 1.10 and the SPI forecast is 40 ÷ 1.10 ≈ 36 days. Independently, the team is 40% done after 12 days, so pace remaining time is 18 days and a projected total of 30. Those two forecasts disagree. The SPI number trusts the baseline’s planned value curve. The pace number trusts units or percent complete. If the baseline front-loaded easy work, SPI looks good while pace already says you will miss. Quote both, then pick the conservative one for an external date. The estimated time remaining calculator is the pace method; this page is SPI only. The time to completion guide is the umbrella that tells you to name which method you used.
EV and PV must share a unit: hours, days or money. Mixing $ earned with hours planned produces a meaningless SPI. Planned duration in the forecast must match that baseline’s time unit. A 40-week plan with SPI 0.8 is a 50-week forecast, not a 50-day forecast. Recalculate on a fixed weekday so you can see direction. One printout of 0.93 is a snapshot; three weeks of 0.93, 0.90, 0.86 is a trend. That trend is what overseeing timeline execution is for. Bands for a single SPI value live on what SPI means.
Forecast duration = planned duration ÷ SPI. SPI = earned value ÷ planned value.
A forecast of 25 weeks if the pace stays the same. See the bands on what SPI means.
Yes. You have earned more than planned by this date. Verify the baseline before you celebrate.
No. Remaining time uses percent or units complete. SPI uses earned value against a baseline. They should be close; if they are not, one of the inputs is wrong.
Not for SPI. Actual cost is for CPI and cost forecasts.
The SPI calculator.
Written by Umesh Manral. Formulas checked against the site's test suite on 11 November 2026. Last updated 10 November 2026. Formulas and tests: methodology. Report a calculation error.