How to Forecast Completion Using SPI

Turn earned value and planned value into a duration forecast, then read it against last week and against remaining-time pace.

Quick answer

To forecast completion with SPI, divide the planned duration by SPI. SPI = EV ÷ PV. If EV is 80 and PV is 100, SPI is 0.80 and a 20-week plan forecasts 25 weeks. The forecast assumes the current rate continues. Read the index in words on the SPI meaning page.

SPI forecast

SPI = EV ÷ PV. Forecast duration = planned ÷ SPI.

Using SPI as a time forecast

SPI tells you how much of the planned work is done relative to the plan, not how people feel. Once you have SPI, the duration forecast is a division. That is the same math as the schedule variance and SPI calculator.

Plain-language bands for 0.5 through 1.5 are on what SPI means. Weekly use of the number is in overseeing timeline execution. The term is in the SPI glossary.

SPI forecast formulas

SPI = EV ÷ PV

forecast duration = planned duration ÷ SPI

delay = forecast − planned duration

EV and PV must use the same unit (money or hours). Planned duration can be days or weeks; the forecast uses that unit.

Worked examples

Each example uses numbers you can load into the calculator above; the results match the tool exactly.

Example 1: EV 80,000, PV 100,000, 20-week plan

SPI = 0.80. Forecast = 20 ÷ 0.80 = 25 weeks. Delay = 5 weeks. These are the mini-calculator defaults.

Load this example

When the forecast is a lie

Early EV is often the easy work. An SPI of 1.1 in week two can still hide a brutal integration. Pair SPI with a look at which tasks are done. If only low-risk tasks are complete, do not cut the date.

SPI versus percent complete

Percent complete remaining time uses your current pace from the start of the job. SPI uses the baseline’s planned value. If the baseline was fantasy, SPI’s forecast is fantasy too. Fix the baseline, or switch to remaining-time pace.

Reading the forecast next to remaining time

Suppose the plan is 40 working days, EV is 110 and PV is 100, so SPI is 1.10 and the SPI forecast is 40 ÷ 1.10 ≈ 36 days. Independently, the team is 40% done after 12 days, so pace remaining time is 18 days and a projected total of 30. Those two forecasts disagree. The SPI number trusts the baseline’s planned value curve. The pace number trusts units or percent complete. If the baseline front-loaded easy work, SPI looks good while pace already says you will miss. Quote both, then pick the conservative one for an external date. The estimated time remaining calculator is the pace method; this page is SPI only. The time to completion guide is the umbrella that tells you to name which method you used.

Units and a weekly habit

EV and PV must share a unit: hours, days or money. Mixing $ earned with hours planned produces a meaningless SPI. Planned duration in the forecast must match that baseline’s time unit. A 40-week plan with SPI 0.8 is a 50-week forecast, not a 50-day forecast. Recalculate on a fixed weekday so you can see direction. One printout of 0.93 is a snapshot; three weeks of 0.93, 0.90, 0.86 is a trend. That trend is what overseeing timeline execution is for. Bands for a single SPI value live on what SPI means.

How to forecast with SPI

  1. Read EV and PV at the same status date.
  2. SPI = EV / PV. PV must be greater than zero.
  3. Forecast = planned duration / SPI.
  4. Compare with last week’s forecast. Direction matters more than one printout.
  5. Read the band on the SPI meaning page before you brief anyone.

Assumptions, limits and common mistakes

Assumptions and limits

  • Straight-line: tomorrow looks like today. Recovery plans are extra work, not a better SPI formula.
  • Needs a baseline. No PV, no SPI.

Common mistakes

  • Using PV ÷ EV (the reciprocal) and calling it SPI.
  • Mixing dollars of EV with hours of PV.
  • Treating SPI 1.0 as proof of quality. It only says the amount of planned work is done.

Frequently asked questions

How do you use SPI to estimate time to complete?

Forecast duration = planned duration ÷ SPI. SPI = earned value ÷ planned value.

What does an SPI of 0.8 mean for a 20-week plan?

A forecast of 25 weeks if the pace stays the same. See the bands on what SPI means.

Can SPI be greater than 1?

Yes. You have earned more than planned by this date. Verify the baseline before you celebrate.

Is this the same as estimated time remaining?

No. Remaining time uses percent or units complete. SPI uses earned value against a baseline. They should be close; if they are not, one of the inputs is wrong.

Do I need actual cost to forecast time?

Not for SPI. Actual cost is for CPI and cost forecasts.

Where do I run the numbers?

The SPI calculator.

Written by . Formulas checked against the site's test suite on 11 November 2026. Last updated 10 November 2026. Formulas and tests: methodology. Report a calculation error.