Example 1: SPI 0.8 on a 20-week plan
- EV 40,000 ÷ PV 50,000 = 0.8, which means 80% of the planned progress.
- Forecast = 20 ÷ 0.8 = 25 weeks: a delay of 5 weeks.
A plain-language reading of every SPI value from 0.5 to 1.5, with the forecast duration and delay it implies.
An SPI of 1.0 means the project is exactly on schedule. Below 1 it is behind: 0.8 means only 80% of the planned progress is done, so a 20-week plan forecasts 25 weeks. Above 1 it is ahead: 1.1 means 110% of the plan. SPI is earned value divided by planned value.
Open the schedule variance and SPI calculator
The schedule performance index (SPI) compares the work you have finished with the work you planned to have finished by now. It is a ratio, so it has no unit, and it reads the same for a 10,000 project as for a 10 million one. This page explains what each SPI value means, shows the delay each implies for a 20-week plan, and lists the traps in reading it. To calculate your own, use the schedule variance and SPI calculator.
SPI is earned value (EV) divided by planned value (PV). Earned value is the planned value of the work that is actually done. If you planned 50,000 of work by this week and finished work that was planned at 40,000, SPI is 0.8.
SPI = EV ÷ PV forecast duration = planned duration ÷ SPI
An SPI of 0.5 doubles the duration, 0.8 lengthens it by a quarter, 1.25 shortens it by a fifth. Because the forecast divides by SPI, the effect is not symmetrical: a project at 0.8 is 25% late, while one at 1.25 is only 20% early.
Each example uses numbers you can load into the calculator above; the results match the tool exactly.
This table uses a 20-week plan. For another plan length multiply the forecast by length ÷ 20. The band names are the ones the calculator shows.
| SPI | Band | Planned progress achieved | Forecast duration | Delay against 20 weeks |
|---|---|---|---|---|
| 0.5 | Seriously behind | 50% | 40 weeks | 20 weeks late |
| 0.6 | Seriously behind | 60% | 33.33 weeks | 13.33 weeks late |
| 0.7 | Behind | 70% | 28.57 weeks | 8.57 weeks late |
| 0.8 | Behind | 80% | 25 weeks | 5 weeks late |
| 0.9 | Slightly behind | 90% | 22.22 weeks | 2.22 weeks late |
| 1.0 | On schedule | 100% | 20 weeks | None |
| 1.1 | Ahead | 110% | 18.18 weeks | 1.82 weeks early |
| 1.2 | Well ahead | 120% | 16.67 weeks | 3.33 weeks early |
| 1.3 | Well ahead | 130% | 15.38 weeks | 4.62 weeks early |
| 1.4 | Well ahead | 140% | 14.29 weeks | 5.71 weeks early |
| 1.5 | Well ahead | 150% | 13.33 weeks | 6.67 weeks early |
SPI is based on value, not on the critical path. A project can show a good SPI because easy, high-value work was finished early, while the task that sets the end date is late. Always compare SPI with the critical path. Also note that SPI drifts to 1.0 at the end of any project, since EV equals PV once everything is finished; the figure is most meaningful in the middle of the project. SPI around 0.9 on a long project is normal noise; the same value two weeks before the end is a real delay.
Only 80% of the planned progress has been achieved. At that pace a 20-week plan takes 25 weeks, a delay of 5 weeks.
The project is exactly on schedule: earned value equals planned value.
Half of the planned progress is done, so the project is on course to take twice as long as planned unless something changes.
More work is complete than planned, so the project is ahead. Check the plan was realistic and quality is intact.
It is a small slip: a 20-week plan forecasts 22.2 weeks. On a long project it is within normal variation; watch the trend.
Schedule variance (EV − PV) is a difference in value; SPI (EV ÷ PV) is a ratio. SPI is easier to compare across projects of different sizes.
Last updated 19 October 2026. Formulas and tests: methodology.