Example 1: 4, 6 and 14 days
- TE = (4 + 4 × 6 + 14) ÷ 6 = 42 ÷ 6 = 7 days
- σ = (14 − 4) ÷ 6 = 1.67 days
- Variance = 1.67² ≈ 2.78
These are the mini-calculator defaults and the quick PERT example on the homepage.
The PERT weighted average of optimistic, most likely and pessimistic duration, with the standard deviation that sits beside it.
Expected time in PERT is TE = (O + 4M + P) ÷ 6, with O at most M at most P. The most likely value gets four times the weight of each tail. For 4, 6 and 14 days, TE is 7 days, not 6, because the pessimistic tail pulls the mean up.
TE = (O + 4M + P) ÷ 6.
Expected time is a weighted average of three durations you already chose: optimistic, most likely and pessimistic. It is not a guess pulled from thin air, and it is not a commitment. Pair it with standard deviation when you need a range or an on-time probability.
The mini-calculator above uses the same formula as the PERT calculator. Many tasks on one path belong there. The probability step is in how to calculate project completion probability. The term itself is defined at expected time.
TE = (O + 4M + P) ÷ 6
σ = (P − O) ÷ 6 variance = σ²
O, M and P must be in the same unit. The 4 in 4M is why TE sits near the most likely value unless P is far away.
Each example uses numbers you can load into the calculator above; the results match the tool exactly.
These are the mini-calculator defaults and the quick PERT example on the homepage.
TE = (5 + 24 + 8) ÷ 6 = 6.17 hours. σ = 3 ÷ 6 = 0.5 hours. When O and P hug M, TE almost equals M. That is a familiar task, not a reason to skip the three points.
Use TE when the pessimistic tail is real (new vendor, first integration, weather). Use M only as a working assumption you will not bet a date on. A Monte Carlo range on the project duration simulator is the next step when many tasks interact.
Add TE along one path. Adding every task in the project double-counts parallel work. That is why the critical path still matters: you need to know which chain you are summing.
Classic PERT treats the three-point estimate as a beta-like distribution with mean (O + 4M + P) ÷ 6. The four on M says “most of the probability sits near the mode.” The one on P still pulls the mean to the right when the tail is long. That is why TE is usually a little larger than M, and why a date equal to M is not a 50% date. If your pessimistic value is barely larger than M, TE and M will be almost the same and you should ask whether P is honest. If P is twice M, TE moves noticeably and a deadline at M is optimistic. None of this is a substitute for historical data: if you have ten similar tasks, a sample mean beats a three-point guess. Use TE when you do not have that sample and you still need one number to put on a path.
Each task’s σ is (P − O) ÷ 6. Variance is σ². On one path, add the variances, then take the square root for the path σ. Do not add the standard deviations; that overstates spread. Do not add variances from parallel tasks that are not on the path you are dating. The on-time probability guide uses that path σ with a deadline. The glossary pages for expected time and variance keep the two formulas next to each other so they are not mixed up in a status report.
TE = (O + 4M + P) ÷ 6. For 4, 6 and 14 the result is 7.
The pessimistic tail is usually longer than the optimistic tail, so the mean sits to the right of M.
Hours, days or weeks, as long as O, M and P use the same one.
Variance uses (P − O) ÷ 6, not TE. You need both for a probability.
Sum TE on the path that sets the date, not every task. Use the PERT calculator for several tasks.
Classic PERT, documented on the methodology page.
Written by Umesh Manral. Formulas checked against the site's test suite on 11 November 2026. Last updated 10 November 2026. Formulas and tests: methodology. Report a calculation error.