Project Time CalculatorProject Time Calculator

Project Time Word Problems, Worked and Checked

Solved problems for effort ÷ people, remaining time from percent complete, unit conversions and adding hours, with a variation on each one.

Quick answer

Project-time word problems are effort divided by people, remaining time from percent complete, or hours and minutes added in base 60. 720 person-days with 5 people is 144 working days. 40% done in 2 hours leaves 3 hours. Always name the unit before you divide.

Effort to duration

Working days = ⌈ effort ÷ (people × hours/day × availability) ⌉.

How to read a project-time word problem

Textbook problems reuse a few patterns. Name the quantity (effort, duration, people, or clock time), write the formula, then convert units only once at the end. The problems below are original variations, not copied exam wording. Every answer is checked in tests/word-problems.test.js.

Use the project time calculator for effort and team size, the person-days calculator when the figure is already in person-days, and the estimated time to complete calculator for percent-complete remaining time.

The handful of formulas these problems use

duration = effort ÷ people    people = effort ÷ duration

person-days = people × days    remaining = elapsed ÷ fraction − elapsed

months ≈ weeks ÷ 4  or  weeks ÷ 4.33    total minutes = 60 × hours + minutes

Worked examples

Each example uses numbers you can load into the calculator above; the results match the tool exactly.

Example 1: 720 person-days and a five-person team

A plan is 720 person-days of work. Five people can share it fully.

  • Duration = 720 ÷ 5 = 144 working days (28.8 weeks at 5 days/week)
  • If the deadline is 30 working days, people = 720 ÷ 30 = 24 people

Variation: at 80% availability those 144 days become 144 ÷ 0.8 = 180 working days. Try it on the person-days calculator.

Load this example

Example 2: 40% done in 2 hours

A job is 40% complete after 2 hours at a steady pace.

  • Projected total = 2 ÷ 0.40 = 5 hours
  • Remaining = 5 − 2 = 3 hours

Same method: 38% in 2.5 weeks → total 2.5 ÷ 0.38 = 6.58 weeks, remaining 4.08 weeks. One-third done in 9 days → total 27 days, remaining 18. Load 40% / 2 hours in the estimated time remaining calculator.

Load this example

Proportional teams

Three people finish a job in 5 days. The work is 3 × 5 = 15 person-days. Five people take 15 ÷ 5 = 3 days, if the work can actually be split. Variation: 4 people would take 15 ÷ 4 = 3.75 days, which rounds up to 4 working days on a calendar. The duration from effort calculator does that rounding for hours as well.

Weeks to months

24 weeks is 24 ÷ 4 = 6 months if you treat a month as 4 weeks. Using 52 ÷ 12 ≈ 4.33 weeks per month, 24 ÷ 4.33 ≈ 5.54 months. State which month length you used. Variation: 10 weeks is 2.5 months at 4 weeks/month, or 2.31 months at 4.33.

Adding task times

1 hour 25 minutes plus 45 minutes: 25 + 45 = 70 minutes = 1 hour 10 minutes, plus the 1 hour already there, so 2 hours 10 minutes (130 minutes). Variation: add another 50 minutes and you have 3 hours 00 minutes. Use the adding hours and minutes tool when the list is longer.

Person-weeks

12 person-weeks with 3 people is 12 ÷ 3 = 4 weeks of duration. Variation: the same 12 person-weeks with 2 people is 6 weeks. Convert person-weeks to hours only after you name hours per day and days per week; the hours to working days page does the conversion without a team size.

A date window, not an effort figure

If the problem already names a start and end date, count working days in the window with the project duration calculator rather than dividing effort. Mixing “60 calendar days” with “60 working days” is the usual trap.

A sequence that works on almost every problem

  1. Underline the unit the answer must use (people, days, hours, months).
  2. Write effort as people × time or as a given person-day total.
  3. Divide only matching units. Convert weeks to days before dividing by people.
  4. For percent complete, remaining = elapsed ÷ fraction − elapsed.
  5. For clock time, add minutes in base 60, then hours.
  6. Check with a calculator on this site using the same numbers.

Assumptions, limits and common mistakes

Assumptions and limits

  • These problems assume work can be split across people with no extra coordination cost.
  • Percent-complete remaining time assumes a constant pace.
  • Month length is a convention (4 or 4.33 weeks), not a calendar.

Common mistakes

  • Treating person-days as calendar days. 144 person-days is not 144 days on the wall.
  • Dividing people by days instead of effort by people.
  • Using 100 minutes in an hour when adding clock times.
  • Converting 24 weeks to 24 months.

Frequently asked questions

How many days is 720 person-days with 5 people?

144 working days, because duration = 720 ÷ 5. At five days a week that is 28.8 weeks.

How many people do I need to finish 720 person-days in 30 days?

24 people, if the work can be shared: 720 ÷ 30 = 24.

If 3 people take 5 days, how long do 5 people take?

3 days. The job is 15 person-days; 15 ÷ 5 = 3.

How much time is left if 40% took 2 hours?

3 hours. Total = 2 ÷ 0.4 = 5; remaining = 3.

Is 24 weeks equal to 6 months?

Yes if a month is 4 weeks. At 4.33 weeks per month it is about 5.54 months. Say which you used.

What is 1 hour 25 minutes plus 45 minutes?

2 hours 10 minutes (130 minutes).

Written by . Formulas checked against the site's test suite on 11 November 2026. Last updated 10 November 2026. Formulas and tests: methodology. Report a calculation error.