Project Time CalculatorProject Time Calculator

Person-Days Calculator: Convert Person-Days to Working Days

Enter person-days or person-weeks and the team size to get working days, weeks and a finish date, or the people a deadline needs.

Quick answer

Working days = person-days ÷ people, rounded up after availability. 720 person-days with 5 people is 144 working days, or 28.8 weeks on a 5-day week. A person-week is one person working one week: 5 person-days when the week is 5 days.

Full-time equivalents.
Share of the day on this project.
Extra effort for risk.
5 = Monday to Friday.
Needed for the finish date.
Dates as YYYY-MM-DD, separated by commas or spaces.

How to read your result

Use this calculator when the estimate is already in person-days or person-weeks and you want working days, weeks and a finish date. It uses the same effort-and-capacity math as the project time calculator, with hours per day cancelling out so 720 ÷ 5 is exactly 144.

  • Working days: person-days (or person-weeks converted to person-days) divided by people × availability, rounded up.
  • Weeks: working days divided by working days per week.
  • Finish date: that many working days counted from the start date, skipping weekends and holidays.
  • People needed (deadline mode): person-days divided by the working days you have, rounded up.

Person-days formulas

person-days = person-weeks × working days per week

working days = ⌈ person-days × (1 + buffer % ÷ 100) ÷ (people × availability % ÷ 100) ⌉

weeks = working days ÷ working days per week

people needed = ⌈ person-days × (1 + buffer % ÷ 100) ÷ (working days available × availability % ÷ 100) ⌉

The shared engine converts person-days to hours with the site's hours-per-day figure and then divides by team capacity. The hours cancel, so the result matches dividing person-days by people. For a cost or an hours figure, use the duration from effort calculator.

Worked examples

Each example uses numbers you can load into the calculator above; the results match the tool exactly.

Example 1: 720 person-days with 5 people

A project will take 720 person-days. Five people, fully available, no buffer, five-day week, start Monday 2 November 2026.

  • Working days = 720 ÷ 5 = 144
  • Weeks = 144 ÷ 5 = 28.8
  • Finish date = Thursday 20 May 2027 (200 calendar days)

These are the calculator's default inputs with the start date set to 2 November 2026.

Load this example

Example 2: 40 person-weeks, 2 people, 80% available

40 person-weeks on a 5-day week is 200 person-days. Two people at 80% availability:

  • Effective people = 2 × 0.80 = 1.6
  • Working days = 200 ÷ 1.6 = 125
  • Weeks = 125 ÷ 5 = 25

Load this example

Example 3: people needed for a deadline (inverse)

200 person-days must finish in 25 working days, fully available, no buffer.

  • People = 200 ÷ 25 = 8 people

If availability is 80%, people = 200 ÷ (25 × 0.80) = 10.

Load this example

How to convert person-days by hand

  1. Get everything in person-days. Multiply person-weeks by working days per week (5 on a Monday–Friday week).
  2. Apply the buffer if you have one: multiply by 1 + buffer as a decimal.
  3. Divide by people × availability. 720 ÷ 5 = 144. At 80% availability, 720 ÷ 4 = 180.
  4. Round up to a whole number of working days.
  5. Divide by days per week for weeks, and count working days on a calendar for the finish date.

Assumptions, limits and common mistakes

Assumptions and limits

  • Work is assumed to split evenly across the people you enter. Dependencies need the critical path calculator.
  • Hours per day cancel in this conversion. For a cost in currency, use the project time calculator with an hourly rate.
  • Working weeks are the first N days of the week. Sunday-first weeks are not modelled.
  • Holidays are only the dates you type.

Common mistakes

  • Treating person-days as calendar days. 720 person-days is not 720 days on the wall unless one person does all of it.
  • Forgetting availability. Five people at 80% are 4 full-time equivalents, not 5.
  • Mixing person-weeks with a 7-day calendar. Convert with the same working days per week you use in the plan.
  • Rounding down. 144.1 working days still needs 145 days of attendance.

Frequently asked questions

How do I convert person-days to working days?

Divide person-days by the number of people, then by availability as a decimal, and round up. 720 person-days with 5 people is 144 working days when everyone is fully available.

How many days is 720 person-days with 5 people?

144 working days, or 28.8 weeks on a 5-day week, if the work splits evenly and there is no buffer. Load it with the button on example 1.

What is the difference between person-days and person-weeks?

A person-week is one person working one week. On a 5-day week that is 5 person-days; on a 6-day week it is 6. Switch the unit on this calculator rather than multiplying in your head.

How do I convert person-days to calendar dates?

First get working days as above, enter a start date, and list holidays. The calculator counts only working days and returns the finish date. 144 working days from Monday 2 November 2026 finish on Thursday 20 May 2027.

How many people do I need for a person-day budget and a deadline?

Divide person-days by the working days you have, then by availability, and round up. 200 person-days in 25 working days needs 8 people at 100% availability.

Is this the same math as the project time calculator?

Yes. That calculator also accepts person-days; this page is the shorter form for that unit, with the 720-and-5-people case as the default worked example.

Written by . Formulas checked against the site's test suite on 11 November 2026. Last updated 3 November 2026. Formulas and tests: methodology. Report a calculation error.