Schedule Performance Index (SPI)
SPI compares the work you have earned with the work the plan said would be done by now.
SPI = EV ÷ PV. Forecast duration = planned duration ÷ SPI. SPI of 1 is on plan; 0.8 means you need 25% more time at this pace.
SPI forecast
SPI = EV ÷ PV. Forecast duration = planned ÷ SPI.
Earned value (EV) is the budgeted value of work actually finished. Planned value (PV) is what the baseline said would be finished by this date. Their ratio is SPI. It is unit-free, so $80,000 earned against $100,000 planned is 0.8 whether you think in dollars or hours.
An SPI of 0.8 on a 20-week plan forecasts 25 weeks (20 ÷ 0.8) if the pace does not change. That is a straight-line forecast, not a law. Read the bands on what SPI means and the walkthrough in forecast completion with SPI.
SPI does not see quality or remaining difficulty. Pair it with a percent-complete pace check on the estimated time remaining calculator.
Formula
SPI = EV / PV forecast = planned duration / SPI
Owning tool: Open the SPI calculator.
Related terms: What does SPI mean · Forecast completion with SPI.