Velocity (Agile)
Velocity is how many story points a team actually finishes in a sprint, used to forecast remaining sprints.
Sprints needed = ⌈ remaining points ÷ velocity ⌉. Forecast with a slow, average and fast velocity from recent sprints.
Sprints needed
Sprints = ⌈ backlog points ÷ velocity ⌉.
Velocity is an observed throughput, not a target you raise in a meeting. Count points completed in each of the last three to five sprints. The average is the usual forecast; the lowest and highest give a range of release dates.
Do not mix people onto a new team and keep the old velocity. Do not convert points to hours unless you have your own ratio: points are relative, hours are not. If you do need hours, the story points to hours note shows the arithmetic and its limits.
Turn sprints into a calendar with the sprint time calculator, then into working days with the project duration calculator if the release window is already fixed.
Formula
sprints = ⌈ backlog points ÷ velocity ⌉
Owning tool: Open the sprint time calculator.
Related terms: How to calculate sprint count · Story points to hours.