Example 1 (simple): 160 hours at 8 hours a day
- Working days = 160 ÷ 8 = 20 days
- Working weeks = 20 ÷ 5 = 4 weeks
These are the calculator's default inputs.
Turn a number of hours into working days and weeks, or working days into hours, using your own length of working day.
Working days = hours ÷ hours per working day. At 8 hours a day, 160 hours is 20 working days, or 4 five-day weeks. To go the other way, multiply days by hours per day: 15 days at 7.5 hours is 112.5 hours. Use your real productive hours, not the length of the paid day.
Choose a direction, enter a value, and set the length of your working day and week.
The result is a count of working time, not a date. To turn the count into a finish date that skips weekends and holidays, use the project time calculator.
working days = hours ÷ hours per working day
working weeks = working days ÷ working days per week
hours = working days × hours per working day
Rounding up to whole days is ⌈ working days ⌉. Nothing else is involved: the calculator does not change the hours or assume breaks, because the hours per day input is meant to be the time you actually expect to spend working.
Each example uses numbers you can load into the calculator above; the results match the tool exactly.
These are the calculator's default inputs.
A freelancer has quoted 250 hours. Between email, calls and admin, a realistic day of project work is 6.5 hours.
At a full 8 hours a day the same job looks like 31.25 days, which is more than a week shorter. That difference is why the hours per day input matters.
A contractor is booked for 15 working days at 7.5 hours a day.
These values assume a five-day week. Use the calculator for any other combination.
| Hours | At 6 h/day | At 7 h/day | At 8 h/day | Weeks at 8 h/day |
|---|---|---|---|---|
| 40 | 6.67 days | 5.71 days | 5 days | 1 weeks |
| 80 | 13.33 days | 11.43 days | 10 days | 2 weeks |
| 160 | 26.67 days | 22.86 days | 20 days | 4 weeks |
| 320 | 53.33 days | 45.71 days | 40 days | 8 weeks |
Divide the hours by the hours in a working day. For an 8-hour day, 40 hours is 5 days and 160 hours is 20 days.
One working day, if your working day is 8 hours long. At 6 hours a day, 8 hours is 1.33 days.
Five days at 8 hours a day, 5.71 days at 7 hours a day and 6.67 days at 6 hours a day. At 8 hours a day that is one working week.
Multiply the working days by hours per day. Fifteen days at 7.5 hours a day is 112.5 hours.
A working day is a day on which work normally happens, usually Monday to Friday. A calendar day is any day. Ten working days normally span 14 calendar days, because they include two weekends.
Only if the person really spends 8 hours on the work. Many teams plan with 6 to 7 productive hours because of meetings and interruptions. The results are only as realistic as that input.
At 8 hours a day and 5 days a week, 160 hours is 4 working weeks.
First convert the hours into working days, then count that many working days forward from the start date while skipping weekends and holidays. The project time calculator does this and also handles team size and buffer.