Person-Days Calculator: Convert Person-Days to Working Days
Enter person-days or person-weeks and the team size to get working days, weeks and a finish date, or the people a deadline needs.
Quick answer
Working days = person-days ÷ people, rounded up after availability. 720 person-days with 5 people is 144 working days, or 28.8 weeks on a 5-day week. A person-week is one person working one week: 5 person-days when the week is 5 days.
How to read your result
Use this calculator when the estimate is already in person-days or person-weeks and you want working days, weeks and a finish date. It uses the same effort-and-capacity math as the project time calculator, with hours per day cancelling out so 720 ÷ 5 is exactly 144.
Working days: person-days (or person-weeks converted to person-days) divided by people × availability, rounded up.
Weeks: working days divided by working days per week.
Finish date: that many working days counted from the start date, skipping weekends and holidays.
People needed (deadline mode): person-days divided by the working days you have, rounded up.
Person-days formulas
person-days = person-weeks × working days per week
working days = ⌈ person-days × (1 + buffer % ÷ 100) ÷ (people × availability % ÷ 100) ⌉
weeks = working days ÷ working days per week
people needed = ⌈ person-days × (1 + buffer % ÷ 100) ÷ (working days available × availability % ÷ 100) ⌉
The shared engine converts person-days to hours with the site's hours-per-day figure and then divides by team capacity. The hours cancel, so the result matches dividing person-days by people. For a cost or an hours figure, use the duration from effort calculator.
Worked examples
Each example uses numbers you can load into the calculator above; the results match the tool exactly.
Example 1: 720 person-days with 5 people
A project will take 720 person-days. Five people, fully available, no buffer, five-day week, start Monday 2 November 2026.
Working days = 720 ÷ 5 = 144
Weeks = 144 ÷ 5 = 28.8
Finish date = Thursday 20 May 2027 (200 calendar days)
These are the calculator's default inputs with the start date set to 2 November 2026.
Get everything in person-days. Multiply person-weeks by working days per week (5 on a Monday–Friday week).
Apply the buffer if you have one: multiply by 1 + buffer as a decimal.
Divide by people × availability. 720 ÷ 5 = 144. At 80% availability, 720 ÷ 4 = 180.
Round up to a whole number of working days.
Divide by days per week for weeks, and count working days on a calendar for the finish date.
Assumptions, limits and common mistakes
Assumptions and limits
Work is assumed to split evenly across the people you enter. Dependencies need the critical path calculator.
Hours per day cancel in this conversion. For a cost in currency, use the project time calculator with an hourly rate.
Working weeks are the first N days of the week. Sunday-first weeks are not modelled.
Holidays are only the dates you type.
Common mistakes
Treating person-days as calendar days. 720 person-days is not 720 days on the wall unless one person does all of it.
Forgetting availability. Five people at 80% are 4 full-time equivalents, not 5.
Mixing person-weeks with a 7-day calendar. Convert with the same working days per week you use in the plan.
Rounding down. 144.1 working days still needs 145 days of attendance.
Frequently asked questions
How do I convert person-days to working days?
Divide person-days by the number of people, then by availability as a decimal, and round up. 720 person-days with 5 people is 144 working days when everyone is fully available.
How many days is 720 person-days with 5 people?
144 working days, or 28.8 weeks on a 5-day week, if the work splits evenly and there is no buffer. Load it with the button on example 1.
What is the difference between person-days and person-weeks?
A person-week is one person working one week. On a 5-day week that is 5 person-days; on a 6-day week it is 6. Switch the unit on this calculator rather than multiplying in your head.
How do I convert person-days to calendar dates?
First get working days as above, enter a start date, and list holidays. The calculator counts only working days and returns the finish date. 144 working days from Monday 2 November 2026 finish on Thursday 20 May 2027.
How many people do I need for a person-day budget and a deadline?
Divide person-days by the working days you have, then by availability, and round up. 200 person-days in 25 working days needs 8 people at 100% availability.
Is this the same math as the project time calculator?
Yes. That calculator also accepts person-days; this page is the shorter form for that unit, with the 720-and-5-people case as the default worked example.