Critical Path

The critical path is the longest chain of dependent tasks and the reason the project cannot finish sooner.

Quick answer

The critical path is the sequence of tasks with zero total float. Its length is the project duration.

Earliest start and finish

ES = max predecessor EF; EF = ES + duration.

Adding every task’s duration usually overstates the work, because some tasks run in parallel. The duration that matters is the longest chain of finish-to-start links. That chain is the critical path. Delay any task on it and the end date moves.

A network can have more than one critical path. Near-critical paths with a day of slack deserve the same attention: a small slip makes them critical too. Crashing a non-critical task wastes money.

Find ES, EF, LS, LF and float with the critical path calculator, then turn the working-day total into calendar dates with the project duration calculator if you already know the window.

Formula

project duration = max EF    critical ⇔ total float = 0