Slack (Total Float) in Project Management
Slack is how long a task can slip before it delays the project end date.
Slack, also called total float, is LS − ES (or LF − EF). Critical tasks have zero slack.
Slack calculator
Total slack = LS − ES (or LF − EF).
Slack is a schedule property, not a feeling that a task has “room”. After a forward pass sets earliest start (ES) and earliest finish (EF), and a backward pass sets latest start (LS) and latest finish (LF), slack is the gap between those two windows. If ES is day 4 and LS is day 7, the task has three days of slack.
Only tasks with zero slack sit on the critical path. A delay there moves the project end date by the same amount. Tasks with slack can slip up to that amount without moving the end, though they may eat free float that a neighbour was counting on.
People mix slack with lag. Lag is a wait you insert between tasks; slack is leftover room in the calendar. To calculate slack on a real network, list predecessors and durations in the slack time guide.
Formula
total slack = LS − ES = LF − EF
Owning tool: Open the critical path calculator.
Related terms: Float · Critical path.