Earliest Finish (EF)
Earliest finish is the soonest a task can be complete: earliest start plus duration.
EF = ES + duration. Project duration is the largest EF in the network.
Earliest start and finish
ES = max predecessor EF; EF = ES + duration.
Once earliest start is known, earliest finish is a single addition. The project cannot finish before the largest EF of any task, because that is the end of the longest chain of work that had to happen in order.
EF is still in project time, not a weekday, until you map it onto a calendar. Weekends and holidays sit outside this number unless you modelled them as duration.
Successors read this EF as a constraint: their ES is at least this EF (plus lag, if you use it). That is the whole forward pass. See latest finish for the matching backward-pass number.
Formula
EF = ES + duration
Owning tool: How to calculate ES, EF, LS and LF.
Related terms: Earliest start ยท Latest finish.
Written by Umesh Manral. Formulas checked against the site's test suite on 11 November 2026. Last updated 10 November 2026. Formulas and tests: methodology. Report a calculation error.