Latest Finish (LF)

Latest finish is the latest a task can end without delaying the project end date.

Quick answer

LF = min(LS of successors), or the project duration if the task has no successors.

Slack calculator

Total slack = LS − ES (or LF − EF).

The backward pass starts at the end. Tasks with no successors get LF equal to the project duration (the maximum EF from the forward pass). Every earlier task must finish in time for its successors’ latest starts.

If two successors have LS of 12 and 15, this task’s LF is 12. Taking 15 would make the first successor late. That “minimum of successors” rule is the mirror of the “maximum of predecessors” rule on the forward pass.

LF minus ES is not float; LF minus EF (or LS minus ES) is. Walk a small network in the ES, EF, LS, LF guide.

Formula

LF = min(LS of successors)  (project duration if none)

Owning tool: How to calculate ES, EF, LS and LF.

Related terms: Latest start · Earliest finish.