Expected Time (PERT)
Expected time is the PERT weighted average of three duration estimates for a task.
TE = (O + 4M + P) ÷ 6, with O ≤ M ≤ P. It sits closer to the most likely value than to the average of O and P.
Expected time (PERT)
TE = (O + 4M + P) ÷ 6.
A single “most likely” guess ignores the long tail of things going wrong. PERT expected time keeps the most likely estimate but weights the pessimistic tail enough to pull TE past M when P is far away. For O = 4, M = 6, P = 14, TE is 7, not 6.
TE is a mean under a beta-distribution approximation, not a promise. Pair it with variance if you need a range or an on-time probability. Sum TE along one path; do not sum every task in the project if some of them run in parallel.
The step-by-step lives in how to calculate expected time. Many tasks at once belong on the PERT calculator.
Formula
TE = (O + 4M + P) ÷ 6
Owning tool: Open the PERT calculator.
Related terms: Variance · How to calculate expected time.
Written by Umesh Manral. Formulas checked against the site's test suite on 11 November 2026. Last updated 10 November 2026. Formulas and tests: methodology. Report a calculation error.