Variance in PERT Estimates

PERT variance measures how spread out a three-point estimate is, from the gap between pessimistic and optimistic.

Quick answer

σ = (P − O) ÷ 6; variance = σ². For a path of independent tasks, add the variances, then take the square root.

Expected time (PERT)

TE = (O + 4M + P) ÷ 6.

The (P − O) ÷ 6 rule treats almost all outcomes as sitting inside plus or minus three standard deviations of the mean, the usual PERT shortcut. A task with O = 4 and P = 14 has σ = 10/6 ≈ 1.67 and variance ≈ 2.78.

When tasks on one path are independent, variances add. Standard deviations do not. Adding σ would overstate the spread. The path σ is what you use for a confidence range around total expected time and for z-scores in the on-time probability guide.

If tasks share the same risk (one vendor, one storm season), independence is a bad assumption and the summed variance is too small. State that limit when you quote a 90% range.

Formula

σ = (P − O) ÷ 6    variance = σ²    σpath = √Σ variance

Owning tool: Open the PERT calculator.

Related terms: Expected time · On-time probability.

Written by . Formulas checked against the site's test suite on 11 November 2026. Last updated 10 November 2026. Formulas and tests: methodology. Report a calculation error.