Latest Start (LS)
Latest start is the latest a task can begin without pushing the project end date.
LS = LF − duration. Total slack is LS − ES.
Slack calculator
Total slack = LS − ES (or LF − EF).
Latest start comes from the backward pass. You first set latest finish from successors (or from the project duration for tasks with none), then subtract duration. If LF is 20 and the task lasts 4, LS is 16.
Compare LS with ES. The difference is total float. When they are equal, the task is critical: you must start at ES, which is also LS.
Starting later than LS guarantees a late project, unless you crash something downstream. That is why LS is the date managers watch once a baseline exists. Compute a whole table with the critical path calculator.
Formula
LS = LF − duration
Owning tool: How to calculate ES, EF, LS and LF.
Related terms: Latest finish · Earliest start.