Lead Time in Project Management
Lead lets a successor start before its predecessor has finished, by a stated overlap.
Lead is overlap on a finish-to-start link: successor ES ≥ predecessor EF − lead.
Earliest start and finish
ES = max predecessor EF; EF = ES + duration.
Lead time in a network is a planned overlap. Writing may start when research is 80% done; installation may start while the last wall is still being painted. That is not the same as procurement lead time (how long a supplier takes to deliver), though both words show up in project talk.
On this site the critical path engine uses finish-to-start with no overlap. To model lead, split the predecessor into “must finish before B starts” and “can finish in parallel”, or start the successor from a partial milestone. Overusing lead hides risk: the overlap assumes the early part of A is enough, which is often the optimistic case.
If the wait is a true pause rather than an overlap, that is lag, not lead.
Formula
successor ES ≥ predecessor EF − lead
Owning tool: Open the critical path calculator.
Related terms: Lag · Earliest start.
Written by Umesh Manral. Formulas checked against the site's test suite on 11 November 2026. Last updated 10 November 2026. Formulas and tests: methodology. Report a calculation error.