Lead Time in Project Management

Lead lets a successor start before its predecessor has finished, by a stated overlap.

Quick answer

Lead is overlap on a finish-to-start link: successor ES ≥ predecessor EF − lead.

Earliest start and finish

ES = max predecessor EF; EF = ES + duration.

Lead time in a network is a planned overlap. Writing may start when research is 80% done; installation may start while the last wall is still being painted. That is not the same as procurement lead time (how long a supplier takes to deliver), though both words show up in project talk.

On this site the critical path engine uses finish-to-start with no overlap. To model lead, split the predecessor into “must finish before B starts” and “can finish in parallel”, or start the successor from a partial milestone. Overusing lead hides risk: the overlap assumes the early part of A is enough, which is often the optimistic case.

If the wait is a true pause rather than an overlap, that is lag, not lead.

Formula

successor ES ≥ predecessor EF − lead

Owning tool: Open the critical path calculator.

Related terms: Lag · Earliest start.