Lag in Project Management
Lag is a planned wait between tasks, such as paint drying before the next coat.
Lag is a delay you add on a finish-to-start link: the successor may not start until predecessor EF plus the lag.
Earliest start and finish
ES = max predecessor EF; EF = ES + duration.
Lag is a relationship, not leftover calendar. You put it on a link because the work itself needs a wait: concrete curing, a client review window, a delivery that cannot be rushed. If task A finishes on day 5 and you need two days of lag, task B cannot start before day 7 even if people are free.
The calculators on this site use finish-to-start links without a separate lag field. To model lag, insert a dummy wait task with duration equal to the lag and no people assigned, or add the wait into the predecessor’s duration if nothing else can start in that gap.
Lag is the opposite idea to lead, which lets a successor start before the predecessor has fully finished. Neither one is slack.
Formula
successor ES ≥ predecessor EF + lag
Owning tool: Open the critical path calculator.
Related terms: Lead time · Float.
Written by Umesh Manral. Formulas checked against the site's test suite on 11 November 2026. Last updated 10 November 2026. Formulas and tests: methodology. Report a calculation error.