Home Extension Time Estimate: Survey to Handover
A worked plan for a typical single-storey rear extension, with dependencies, a critical path and a PERT range. It is a method example, not a builder’s quote.
On this illustrative plan the critical path is 106 working days using most-likely durations. PERT expected time on that path is 110.5 days, with a 90% range of about 99–122 days.
These figures are an illustrative plan for a typical project of this type, not industry statistics. Change the tasks to match your site, team and scope.
The team on this sketch is a lead designer, a planning consultant, and a small build crew (groundworks, carpentry, first-fix trades, plaster, decorate). Durations are working days, not calendar days. Permits sit on the critical path because nothing in the ground starts until the paper is done.
Task list and live results
What usually causes delays
Planning comments that send the drawings around again, a wet week that floods the footings, window lead times that overshoot the roof, and a plasterer who cannot start until both first-fix and windows are closed in. Those four are why permits, foundations, roof and plaster have wide pessimistic tails on this page.
How to read the 106 days
Most-likely durations on the longest chain add to 106 working days. That is about 21 weeks on a five-day week, before holidays. Two chains tie: roof-then-windows versus first-fix; both meet at plaster. A delay on either chain makes that chain the only critical path.
PERT expected time on the first chain is 110.5 days because permits and structure have long pessimistic values. A deadline of 119 working days is about the one-sided 90% duration (TE + 1.28σ). The chance of beating 119 days in this model is about 89%, assuming the tasks are independent, which weather and one crew are not.
Map 106 working days onto a calendar with the project duration calculator. Rebuild the network with your own predecessors in the critical path calculator. Replace single durations with three-point values in the PERT calculator. If you only have a bag of hours, start from the task time estimator.
How to adapt this plan
Replace “permits” with whatever actually gates the groundworks: listed-building consent, party-wall awards, or a building-control notice. If those run in parallel with detailed design, give them a predecessor of survey only and watch whether design stays on the path. A two-storey extension usually lengthens structure and roof, not snagging. A kit-of-parts build can shorten structure and move the path onto windows. Keep first-fix off the path unless the carpenter and the electrician cannot overlap.
Do not treat 106 days as a quote. It is the sum of most-likely working days on one chain for a small crew. Holidays, weather and a single shared labourer will stretch the calendar even if the network is unchanged. If you already have a start and a hoped-for handover, count working days in that window first, then compare with 106. A shortfall is a scope or crew conversation, not a reason to shrink every pessimistic value until the chart fits.
Written by Umesh Manral. Formulas checked against the site's test suite on 11 November 2026. Last updated 10 November 2026. Method: methodology.