Mobile App MVP Time Estimate
A small product team shipping a first store build, where the API and auth sit under the screens that users actually see.
Most-likely critical path is 46 working days. PERT expected time on that path is 48.3 days, with a 90% range of about 43–54 days.
These figures are an illustrative plan for a typical project of this type, not industry statistics. Change the tasks to match your site, team and scope.
The sketch team is a product lead, one designer, two engineers (API and client) and a part-time QA. Store review is folded into “store release” as working days you do not control. Payments can trail core screens because QA waits for both, but auth blocks the screens.
Task list and live results
What usually causes delays
An API contract that changes after screens are drawn, a payment-provider review, a store rejection on permissions copy, and a beta that surfaces one more must-have screen. The pessimistic 20 days on core screens is extra scope, not slower typing.
How to read the 46 days
UX is off the critical path in the most-likely case because the API and auth take longer. If UX slips past day 15, screens wait on design instead of auth and the path flips. Payments have float until they exceed the screen build.
PERT expected time on A–C–D–E–G–H–I is 48.3 days. A 53-day deadline is near the 90% one-sided figure. That is still a working-day count: add weekends and store queues on a calendar.
Rebuild this in the critical path calculator and the PERT calculator. Hour breakdowns belong on the task time estimator. A fixed release window belongs on the project duration calculator.
How to adapt this plan
Drop payments if the MVP is wait-list only; QA then waits only on core screens and the path shortens unless screens already dominate. Add a native-store asset task if screenshots and review copy are not inside “store release.” A designer-heavy team can put UX on the path: if UX’s most-likely duration exceeds API plus auth, screens wait on design. Two client engineers instead of one usually shortens screens, not the API, unless you also split the backend.
Forty-six working days is roughly nine weeks plus weekends. Store review is not a working-day you control; the pessimistic 6 on store release is a placeholder for a bounce, not Apple’s published median. If you already sold a date, count working days to that date and compare with 46 or with the PERT 90% of about 53. A gap is scope (cut payments, cut a screen) or sequence (start API before discovery fully closes — a fast-track with a contract risk), not a reason to set every most-likely equal to the optimistic value.
Written by Umesh Manral. Formulas checked against the site's test suite on 11 November 2026. Last updated 10 November 2026. Method: methodology.