Kitchen Remodel Time Estimate: Strip-Out to Decorate
A small kitchen remodel where the long pole is the unit lead time, not the fitting days on site.
On this plan the critical path is 35 working days, driven by design and made-to-order units. PERT expected time on that path is 36.8 days (90% range about 32–42).
These figures are an illustrative plan for a typical project of this type, not industry statistics. Change the tasks to match your site, team and scope.
This sketch assumes one designer, a fitter, and named plumbing and electrical trades who can overlap after strip-out. The homeowner still lives in the house, so noisy work is weekday-only. Units are made to order; stock kitchens would shrink task C and might move the critical path onto plaster.
Task list and live results
What usually causes delays
A late unit delivery, a worktop template that has to be recut, a hidden leak after strip-out, and a plaster coat that needs an extra day to dry before fitting. The pessimistic 25 days on “order units” is the usual factory plus shipping tail, not a worst-ever container strike.
How to read the 35 days
Strip-out, first fix and plaster run in parallel with the unit lead time. They finish before the units in the most-likely case, so they have float. If plaster slips past day 23, fitting cannot start and plaster joins the critical path.
PERT expected time on A–B–C–H–I–J–K is 36.8 days. A 41-day deadline is roughly the 90% one-sided duration in this model. Live in the house for that whole window; do not plan a dinner party on day 36.
Turn 35 working days into calendar dates with the project duration calculator. Edit predecessors in the critical path calculator. Hour-level fitting lists belong on the task time estimator.
How to adapt this plan
If the units are in stock, cut task C to a few days and the path will likely jump onto plaster. If the worktop is templated off site, add a lag after fitting before the worktop task, or split “fit units” and “template.” A utility-room knock-through adds first-fix and plaster time; it rarely shortens the factory lead. Living elsewhere for a fortnight can let noisy trades overlap more than this weekday-only sketch allows — model that as shorter strip-out and plaster, not as a smaller factory number.
Thirty-five working days is about seven weeks on a five-day week. It is not “a month.” Clients hear “kitchen in four weeks” and count calendar days including weekends. Show both: working days from the network, then dates from the duration calculator with the real start. If the factory quotes 20 working days, replace the most-likely 15 on task C and recompute; do not add 5 days to the project total by hand, because plaster may still finish first.
Written by Umesh Manral. Formulas checked against the site's test suite on 11 November 2026. Last updated 10 November 2026. Method: methodology.