Float in Project Management (Total Float and Free Float)

Float is spare time in a network schedule: total float against the project end, free float against the next task.

Quick answer

Total float = LS − ES. Free float = (earliest successor ES) − EF. Zero total float means the task is critical.

Slack calculator

Total slack = LS − ES (or LF − EF).

Float and slack are the same number when people say “total float”. The useful split is total versus free. Total float is room against the project finish. Free float is room against the next task: you can slip this far and the successor can still start at its earliest start.

A task can have total float and zero free float. That happens when the successor is also waiting on you; any slip of yours pushes that successor’s ES, even if the project end still has spare days further down the chain.

Do not treat float as a bank you can spend twice. Using float on two parallel tasks that share a successor can erase both buffers. The critical path calculator reports both figures so you can see which tasks are actually loose.

Formula

total float = LS − ES    free float = min(ES of successors) − EF

Owning tool: Open the critical path calculator.

Related terms: Slack · Lag.